help customizing Outlook > Tasks > Current view

  • Thread starter KJPnPA
  • Start date Views 797
Status
Not open for further replies.
K

KJPnPA



From Outlook > Tasks > Current view > Next Seven Days > Customize > Filter > SQL I see a drop down list that includes a variety of options. I just don't see the one I need. Is it possible to set the current view of tasks to show just the next 3 weeks (21 days)?

Thank you.
 
R

Roady [MVP]



You can define a new view and then set the filter via the Advanced tab;

Field: Due Date
Condition: between
Value: Now and 3 weeks

There are many more date values that you can simply write which Outlook can understand. For an overview see;
Quickly set dates with formulas and text
 