I setup a task with date July 16th as start date and the same date, July 16th. as due date.
I setup the recurrence as monthly with recurrence on the 16 day of every 1 month.
Therefore, once I mark this task as complete, it should recur to August 16th.
After some days, as the task has not been completed in time, I change the due date to July 25th.
I check the recurrence setup and it remains unchanged as I indicated before.
On July 25th. the task is completed and I expect it to recur to August 16th. but it recurs to August 25th. !!!
It is recurring as if I had chosen one of the other recurrence options which is "recur to 1 month after the task is completed" and not with the recurrence rule I chose.
I have not been able to find what maybe causing this. Help is greatly appreciated. Thx.
I setup the recurrence as monthly with recurrence on the 16 day of every 1 month.
Therefore, once I mark this task as complete, it should recur to August 16th.
After some days, as the task has not been completed in time, I change the due date to July 25th.
I check the recurrence setup and it remains unchanged as I indicated before.
On July 25th. the task is completed and I expect it to recur to August 16th. but it recurs to August 25th. !!!
It is recurring as if I had chosen one of the other recurrence options which is "recur to 1 month after the task is completed" and not with the recurrence rule I chose.
I have not been able to find what maybe causing this. Help is greatly appreciated. Thx.